Home » Key Issues » Pilrow Windfarm

REVISED Planning Inspectorate Action Timetable

Below, please find the revised timetable for the Broadview Windfarm Appeal, as drawn up by Planning Inspectorate.

 

Reference:APP/V3310/A/13/2197449

TOWN AND COUNTRY PLANNING ACT 1990   APPEAL BY Broadview Energy Limited

SITE AT Pilrow Wind Farm, Land East of the M5 and South of A38 Bristol Road, Rooksbridge, Axbridge, Somerset.

 

INSPECTOR: P Jackson. BARCH RIBA

 

ACTION   

TIMETABLE

Start Date 11 June 2013
Submission of Questionnaire 24 June 2013
Deadline for Comments from Interested Parties 26 July 2013
Submission of Statements of Case 5 August 2013
Statement of Common Ground 5 August 2013
Pre-inquiry Meeting

12 November 2013. 10.00am    

Bridgwater House, King Square, Bridgwater, TA6 3AR

Submission of Proofs of Evidence 10 December 2013
Inquiry

9 January 2014, 10.00am 

Princess Hall, Princess Street, 

Burnham On Sea, TA8 1EH

Estimated Number of Sitting Days 6
Report submitted to Secretary of State on or before (provisional) (1) 3 March 2014
Decision Issued on or before (Secretary of State cases) TBA (2)

 (1).The date indicated is provisional. The target date for submission of the report to the Secretary of State will be confirmed within 10 working days of the close of the inquiry.

 (2). In accordance with the requirements of Schedule 2 of the Planning and Compulsary Purchase Act 2004, you will be advised within 10 working days after the close of the Inquiry of the timetable set for    

    the Secretary of State issuing the decision.